# Crane Factory Acceptance Testing: On-Site and Remote Witness

A 32-ton double-girder overhead crane failed the Factory Acceptance Test (FAT) due to a minor issue. Although its structure and mechanical assemblies passed inspection, a fault was found in the hoisting brake: the release clearance on both sides of the brake was inconsistent, measuring 0.4 mm on one side and 0.9 mm on the other. This discrepancy did not surface during no-load testing at the factory. However, two weeks after commissioning on site, the brake used for lifting 30-ton ladles developed uneven pad wear and load drift. While the repair itself took only two hours, the incident caused a ten-day shipment delay.

Buyers often treat the Factory Acceptance Test (FAT) merely as a simple check to confirm whether the equipment can operate. A properly conducted FAT, by contrast, is a quantifiable checklist with clear limit values for every item. It should specify the measurement items, test instruments, acceptance thresholds, record formats, and responsible sign-off parties. Without defined acceptance criteria, the assessment becomes subjective: the supplier deems it acceptable while the buyer rejects it, leading to deadlock.

Remote witness acceptance is also prone to misunderstanding, as many buyers regard it only as a way to avoid business travel. This ambiguous arrangement frequently leads to a typical outcome: the equipment appears fully functional on video, yet fails acceptance once delivered to site. This guide clarifies the test items, required instruments, record formats, camera placement, inherent limitations of remote acceptance, and the handover process to on-site commissioning.

---

## What FAT Covers and What It Leaves Out

### In scope: mechanisms, electrics, safety functions, documents

A factory acceptance test runs in the maker's works, before anything gets packed. It proves mechanism performance, electrical function, safety circuit response, and document completeness under controlled conditions. Typical content covers full-stroke no-load motion, item-by-item limit and stop triggering, running and braking at rated load, measured brake drift, simulated overload, insulation and earthing checks, a spares count, the document pack, and the nameplate details.

FAT earns its place through disassembly, because inside the works the machine still comes apart. So a fault traces straight to a part or a wire, and once the structure closes and the crane reaches site, the same fault costs several times more.

### Out of scope: site conditions and the assembled state

FAT cannot replace the site acceptance test. Four things stay outside it: rail accuracy and measured span, power quality and the earthing system, interference from other equipment on the same bay, and the quality of site weld seams and high-strength bolting.

One more limit gets misread: FAT says nothing about long-term reliability, because a few dozen cycles expose assembly and wiring errors rather than fatigue and wear. Put that in the contract, or a passed FAT slowly turns into a claim that the machine has been life-tested.

---

## Test Order and Acceptance Criteria

Order matters here: no load first, rated load in the middle, overload last, with safety functions checked at every stage. Table one sets out items, method, criteria, and record content.

| Test item | Load and method | Criterion | Record |
| --------- | --------------- | --------- | ------ |
| No-load motion | Empty hook, full stroke 3 times per motion | Direction matches the label, no binding or noise | Stroke time and anomalies |
| Limits, safety chain | Trigger each limit, stop, interlock, overload simulation | Every trigger stops the drive, reset restarts | Count and result per item |
| Rated load running | 1.0 times rated, 3 lifts and runs each way | Speed within 5% to 10% of design, normal temperature | Speed, temperature rise, noise |
| Brake drift | 1.0 times rated, measure slip after braking | No greater than the design figure | Measured and design values together |
| Static test | Commonly 1.25 times rated, held clear | No deformation, cracks, or loose joints | Camber before and after |
| Dynamic test | Commonly 1.1 times rated, each and combined motion | Free movement, reliable braking | Cycle count and result |
| Electrical checks | Insulation, earthing, phase sequence, control voltage | At or above design, continuous earth, correct sequence | Instrument, range, reading |
| Paint, marking | Film thickness, adhesion, nameplate, labels | Meets the coating system, labels legible | Points counted, reading each |

### No-load motion: clear the basic errors first

First, start with no load, which flushes out wiring, phase sequence, and limit setting errors. Run every mechanism through its full stroke, then trigger the emergency stop, door interlock, and overload simulation one at a time. Any motion that runs against its label gets corrected in the works, never on site. Write criteria a crew can tick: correct direction, no binding or noise, and a limit that restarts after reset.

### Rated and overload: dynamic in the works, static on site

Practical limits shape the split, since counterweight and floor loading often make a full static test awkward. So 1.0 times rated running plus 1.1 times dynamic load happens indoors, and the static test waits for site. That arrangement belongs in the contract, because without it a missing static test reads as a defect.

Overload factors follow the applicable standard and the contract, commonly 1.25 times static and 1.1 times dynamic. Hold times come from GB/T 3811, GB/T 14405, GB/T 6067, and the design file. So never invent the number in a tender. Write "per the standard named in the contract, with the bidder stating the factor in the deviation list".

### Braking and drift: criteria need a number to compare

Brake drift, often called load slip, causes more argument than any other FAT item. Many contracts say only that braking must be reliable, yet that phrase decides nothing. A usable clause reads: **the measured value shall not exceed the value given in the design file, and the report shall list measured and design values side by side.** Working values commonly fall between a few millimetres and the mid-teens, moving with hoisting speed, brake type, and load. Compare an [electric hoist](https://yzcranes.com/product-category/electric-hoist/) only against its own design value.

Record the release gap on both sides of each brake too. The usual range runs 0.3 to 1.0 mm, and the two sides should sit close together. In the case above, a 0.5 mm difference was enough to wear one lining faster.

### Limits and safety circuits: trigger each one, no second-hand reports

The safety chain covers hoist limits, travel limits on both axes, buffers, emergency stop, door interlock, overload limiting, and anti-collision where fitted. Then trigger each item once and record it.

Performance level for safety-related control systems follows ISO 13849-1, with PL d and Category 3 common on cranes. Electrical equipment follows IEC 60204-32. In FAT terms those standards ask three questions: two channels, self-monitoring, and a safe state when power drops. Those questions tell you more than a check that a limit switch exists.

---

## Instruments and Records

### What to measure: eight core values

Eight values carry the core record: load, brake drift, mechanism speeds, noise, insulation resistance, earthing continuity, temperature rise, and paint film thickness.

Do not skip geometry, because main girder camber and deflection at rated load follow GB/T 3811 and the duty class, commonly S/700 to S/1000 of the span. Rail and wheel tolerances also follow ISO 12488-1. Measure once in the works and once on site, because the difference shows what transport did.

### What to measure with: instruments need valid calibration

Load comes from a calibrated load cell or test weights. Geometry needs a level or a total station, never a tape and a string line. Speed needs a tachometer or a laser meter. Insulation needs a 500 V or 1000 V megger matched to the rated voltage. Earthing needs a resistance tester. Noise needs a sound level meter with the measuring point written down. Film thickness needs a magnetic or eddy current gauge.

Every record carries instrument model, serial number, and calibration expiry. Leave that column blank and a third-party reviewer sends the report back.

### Record format: one page per item, five columns

One page per test item works well, with five columns: item and method, instrument number, measured value, criterion, and conclusion with signature. The header names model, serial, date, and attendees. Log raw data by hand and photograph the sheet rather than typing it up later.

Agree the report language in the contract, because export projects usually ask for English or a bilingual report.

---

## Remote Witnessing: Camera Positions, Flow, and Limits

### Cameras and light: three fixed positions, no handheld

Remote witnessing succeeds or fails on whether the picture supports a decision. Three positions cover the minimum: a wide shot of the machine, a close shot on brakes and drums, and a close shot on displays. All three need fixed mounts, because handheld footage carries no evidential value at the moment of judgement.

Watch the light, since high windows put mechanisms into silhouette, so add fill light where needed. The instrument camera must catch the display and the gauge scale in one frame.

### Broadcast flow: agenda, roll call, readings, archive

Four habits carry the session: send the agenda 24 hours ahead, so both sides know how long each item takes. Call each item by name, then have the supplier read the value while the buyer confirms it. Then hold the camera on the reading for several seconds. Record everything and send the signed report with the video link within 24 hours.

Without video and item-by-item confirmation, remote witnessing collapses into an ordinary video call.

### What remote work cannot do: put the exclusion list in the contract

Some items resist remote judgement: load tests, because counterweight needs a verified lift; precise brake drift, which needs a fixed scale in the same frame; and weld internal quality, which depends on a testing report. Handle it in writing.

Remote witnessing covers the items on its list, everything else goes to site acceptance, and remote results never replace physical witnessing. On remote projects, Yuzhong splits the two lists into contract annexes before the test day.

| Witness item | On site | Remote | Note |
| ------------ | ------- | ------ | ---- |
| No-load full stroke | Yes | Yes | Wide and mechanism cameras |
| Limits, safety chain | Yes | Yes | Result reported per item |
| Rated load, temperature | Yes | Partly | Temperature needs a close reading |
| Brake drift | Yes | Not advised | Scale and camera share a frame |
| Static, dynamic tests | Yes | No | Counterweight needs a verified lift |
| Insulation, earthing | Yes | Not advised | Meter must fill the frame |
| Weld testing | Yes, report | Yes, report | Electronic report verifiable |
| Geometry, camber | Yes | Not advised | Depends on instrument and station |
| Paint film, appearance | Yes | Partly | Appearance visible, film needs a reading |
| Documents, spares | Yes | Yes | Check against the packing list |

---

## Common Failures and How to Handle Them

### Electrical: phase sequence, wiring, insulation

Reversed phase sequence tops the list, and it shows as a button that drives the wrong direction. Misplaced limit wiring also makes a limit trip in the wrong position. Low insulation resistance usually traces to a damp cabinet or a damaged cable, and it needs a retest after the fix. Missing earthing fails more often on export projects, because local codes there ask for more.

### Mechanical: gaps, alignment, rail contact

Uneven brake gaps, coupling misalignment, uneven wheel contact, a rope jumping its groove, and oil weeping at a gearbox joint all belong here. A short no-load run hides every one of them. Targeted measurement finds them, using a feeler gauge for gaps and a dial indicator for alignment.

### Settings: ramps, calibration, anti-sway

Inverter ramps set too short show up as visible load drift when hoisting brakes. A mis-calibrated overload limiter trips at the wrong load. Anti-sway parameters left at default, without matching the rope length, miss the design damping. None of these change hardware, yet each shapes daily operation.

---

## Linking FAT to Site Commissioning

### The open-items list: a five-column template

A FAT rarely closes with nothing outstanding. What matters is that open items become a list, each with an owner and a closing date. Copy the five columns below.

| No. | Issue | Owner | Close by | Retest |
| --- | ----- | ----- | -------- | ------ |
| P-01 | Brake release gap differs 0.5 mm between sides | Supplier | Before shipment | Feeler gauge, photographed |
| P-02 | Long travel limit trips about 150 mm off | Supplier | Before shipment | 3 full-stroke runs each way |
| P-03 | Earth conductor undersized in the panel | Supplier | Before shipment | Visual check, continuity test |
| P-04 | Spare kit one brake pad set short | Supplier | Before shipment | Count against packing list |
| P-05 | Static test not done in the works | Both sides | Site acceptance | Run at the contract factor |

Close each line before shipment or move it formally to site. Never ship against a verbal promise. At the end of FAT, Yuzhong merges the open-items list, the packing list, and the document list into one confirmation sheet. Loading starts only when all three carry signatures.

### Site retests: five items must run again

Five items need repeating on site, without reusing FAT data: rail accuracy, girder camber, no-load full-stroke motion, safety circuit triggering, and load testing. The first two show what transport and installation did. The last three show whether site assembly and wiring hold up.

File the retest data next to the FAT data, because the gap between the two sets becomes a baseline for judging early deformation.

Treat FAT as a checklist that can be judged rather than a plant tour, and most acceptance disputes shrink. Criteria on paper, readings in the table, signatures on the report: those three carry the weight.

## Frequently Asked Questions

### 1. Must a buyer attend FAT in person?

Not necessarily, since the contract can choose physical witnessing, remote witnessing, or a third-party inspection. Remote work covers no-load motion, limits and safety circuits, control functions, appearance, and document checks. Load testing, precise drift measurement, insulation readings, and weld quality need site work or a third party. If the machine serves a critical process, send one physical visit.

### 2. What overload factor applies?

Common practice runs 1.25 times rated for the static test and 1.1 times for the dynamic test. The exact factor, hold time, and procedure come from the contract standard and the design file. Counterweight and floor capacity often push the static test to site, so write that arrangement into the contract.

### 3. Does remote acceptance hold up?

It does, provided the contract states its effect. A workable clause reads that remote witnessing equals physical witnessing for the listed items, and site acceptance covers everything else. Three supports make the conclusion stick: continuous video from fixed cameras, item-by-item confirmed readings, and a report signed by both sides.

### 4. What happens when something fails?

Split the response. Brakes, limits, safety circuits, and structural defects need correction and retest, with no conditional release. Appearance and document issues can go on the open-items list if each carries a date. Every correction needs a photograph or retest data, because a verbal note proves nothing.

### 5. How does FAT differ from SAT?

FAT runs in the maker's works and proves mechanism performance, electrical function, and document completeness. SAT runs after installation on site and proves rail accuracy, span, assembly quality, and fit with surroundings. Neither replaces the other.