# How to Write a Crane RFQ That Gets Accurate, Comparable Quotes

If your inquiry consists of only a few lines, the quotations you receive will often be very sketchy. This rule holds true almost without exception for crane procurement. If you simply send an email stating “Please quote for one 10-ton overhead crane”, the quotations you get may range from USD 20,000 to USD 80,000 — every supplier will have to guess your actual requirements.

A common misconception is that the more parameters you provide, the higher the price will be. The opposite is true. The vaguer the information, the wider the quotation spread, and the final transaction price tends to be higher. Suppliers have to factor in the risks arising from uncertainty. The half an hour you save filling out the inquiry form may eventually cost you an extra five-figure sum.

Below is an inquiry framework covering ten key data points, drawing requirements, site operating conditions, technical standards, commercial terms, and expectations for the quality of supplier responses.

---

## Why Most Inquiries Come Back With a Useless Quote

### Missing information leaves the supplier guessing

A crane is not a catalogue item. Take two machines with the same 10 t capacity and 20 m span. A duty class anywhere from M3 to M8 changes steel weight, motor rating, brake configuration, and even girder depth by a wide margin. One extra metre of span can force a new girder section, and three extra metres of lift height changes rope length and drum diameter.

When the information arrives incomplete, a supplier faces two choices. Quote the minimum configuration and show an attractive number, or quote the conservative configuration and stay safe. The first route adds cost later, while the second loses the order at first screening.

### The same word means different things to different bidders

"Span 20 m" carries at least three readings: rail centre to rail centre, clear building width, or the hook's effective coverage. Those three can differ by more than two metres.

"Capacity 10 t" is ambiguous as well. Does the figure include the weight of the attachment? Fit a 1.5 t clamp and real lifting capacity drops to 8.5 t. That gap turns into an argument at acceptance.

"Duty class A5" causes the most trouble. The FEM system uses M classes, ISO 4301-1 uses U classes mapped onto A classes, and CMAA uses A to F. The same digit does not describe the same real intensity of use across those systems.

### Without a common basis, the only comparison left is price

Put three quotes on the table with different scopes, different definitions, and different exclusions, and the only thing you can compare is the final total. Decision-making then collapses into price comparison, and nothing else survives. Price comparison usually selects the lowest quote, which also carries the largest later markup.

A good inquiry does not ask a supplier to quote. It makes every supplier quote on the same sheet.

## Ten Data Items Every Supplier Needs

### Capacity, span, and travel

Start with rated capacity, and state whether the figure includes attachment weight. Where a clamp, vacuum pad, or C-hook goes on the hook, write the model and its own weight onto the same line.

Then the span. Write it plainly: "span 20 m, measured rail centre to rail centre". If the rail does not exist yet, give the column pitch and the clear usable width, then ask the supplier to confirm the figure.

Travel length comes next, meaning how far the bridge runs and how far the trolley runs. Travel drives conductor bar, festoon cable, and VFD configuration, and plenty of buyers leave it out.

Two follow-up questions expose the gaps fast: is that span rail centre to rail centre or clear width, and does rated capacity include the attachment?

### Lift height and headroom

Item four is lift height, and the datum needs agreeing. Does the figure run from floor level to the hook's closed position, or from rail top? The two readings differ by the rail height, often 8–12 m, which can change the whole machine.

Item five is the headroom limit, and it decides the trolley. Give the underside elevation of the building beam, the tie chord elevation, and the highest hook point you can accept. A low-headroom solution changes trolley structure, and both price and lead time move with it.

Follow up directly: does that lift height run from floor to hook closed position or from rail top? Ask what clearance separates beam underside and rail top.

### Duty class and real intensity of use

Item six is duty class plus the intensity behind it. Writing "A5" alone does not help a supplier size the structure. Add the rough cycles per day, running hours per shift, and working days per year.

Set the class too low and structural fatigue life falls short, while setting it too high pushes machine price up without adding service life. The judgment has a documented route, since ISO 4301-1 and FEM 1.001 both grade by frequency of use and load spectrum, and domestic projects commonly cite GB/T 3811.

Ask which system the A5 figure follows, and what daily cycle limit it carries.

### Power supply, environment, and local rules

Item seven is power: voltage, phase count, frequency, and supply method, whether conductor bar or cable reel. Values of 380V/50Hz, 415V/50Hz, and 440V/60Hz each point at different motor options, and one wrong line means new motors and new drives.

Item eight is the working environment: indoor or outdoor, minimum and maximum temperature, humidity, corrosive gas, hazardous area classification, and cleanliness level. This item often moves the price further than tonnage does.

Item nine is control method, whether cabin, pendant, or radio remote. Then state any requirement for dual control.

Item ten covers local rules and certification: mandatory approval in the country of installation, documents for customs clearance, and any third-party inspection requirement. Leave this vague on an export project and the machine stops at the border.

| Data item | Vague wording that causes trouble | Consequence of a gap |
| --------- | --------------------------------- | -------------------- |
| Rated capacity | "10 t" | Attachment weight not deducted, real lifting capacity falls short |
| Span | "20 m" | Rail centre distance and clear width mixed up, girder needs recalculation |
| Lift height | "9 m" | Datum unclear, rope and drum configuration drift |
| Travel length | Often omitted | Conductor bar and cable come up short, second purchase needed |
| Duty class | "A5" alone | System unclear, structural fatigue life mismatched |
| Power supply | "three-phase" | Voltage or frequency mismatch, new motors and drives |
| Environment | "inside the workshop" | Corrosion or hazardous area missed, protection level too low |
| Control method | Often omitted | Electrical scope and quote basis disagree |
| Existing rail | Often omitted | Rail model mismatch, retrofit cost added later |
| Rules and certification | Often omitted | Customs clearance blocked or site acceptance fails |

## The Drawing and Photo Pack: One Section View Beats Ten Emails

### Building section and column pitch

The most useful single drawing is the building cross-section. Mark column pitch, rail top elevation, tie chord elevation, corbel positions, and whether the rail already exists. With that sheet in hand, a supplier can work out span, headroom, and the power feed point without a phone call.

A hand sketch with dimensions does the job when no formal drawing exists yet. Sketches get accepted far more often than most buyers expect. Nobody rejects an ugly drawing. Missing dimensions stop it.

### How to shoot site photos

Four photo groups carry the value: rail and supports, power feed and cable route, lifting opening, and nearby obstructions.

Attach one line of notes to each photo, for example "rail in service eight years, QU70". A photo with a scale reference beats a photo without one, so put a tape measure, a signboard, or any object of known size on the floor before shooting.

### Nameplates on existing equipment

For a replacement or a repeat order, photograph the nameplate on the existing machine. Model, capacity, lift height, duty class, and year of manufacture let a supplier narrow the configuration within ten minutes.

Retrofit projects need three more photos: the inside of the control cabinet, the brake assembly, and the wheel-to-rail contact pattern. Those three expose hidden work before it reaches the quote.

## Site Conditions That Move the Price

### Rail and foundation

Whether the rail exists, which model it is, and how accurately the installer set it all feed the number. Where a rail exists but alignment falls short, a supplier either prices the correction or adds a risk allowance.

Foundation and support structure follow the same logic. An overhead crane transfers load into building columns and crane girders, so a girder that needs strengthening adds cost outside the crane contract and slows the whole project.

Ask directly: does the quote include the rail and its alignment, and if not, who signs off rail accuracy?

### Transport and erection

Abnormal loads carry cost that buyers forget. When a girder exceeds container or flatbed limits, it ships in sections and gets spliced on site, which adds high-strength bolted connections, site welding, and re-inspection.

Unloading and erection need the same clarity: who supplies the mobile crane, whether the yard admits a large crane, and whether the site needs a road occupancy permit.

Ask whether the girder ships in one piece or in sections, and if in sections, who splices on site and whether the price includes it.

### Power shutdowns and the installation window

Installation needs the plant to switch off. How long a shutdown the plant can grant, and whether work only fits weekends or the annual overhaul, decides the construction method and the labour cost.

Put that condition into the inquiry, because only then does a delivery promise mean anything. Leave it out and both sides read "45 days delivery" differently: one means arrival on site, the other means ready to use.

Ask whether lead time starts at down payment or at drawing approval, and how long a shutdown commissioning needs.

## Standards, Certification, and Inspection Clauses

### How to specify applicable standards

Do not write "complies with international standards" in an inquiry. Either leave the line out or name the documents: GB/T 3811 for design, GB/T 14405 for general overhead cranes, GB/T 6067 for safety, IEC 60204-32 for electrical equipment, and ISO 13849-1 for safety-related control systems. For Europe you may call up EN 15011, and for North America the relevant clauses of CMAA 70 and OSHA 1910.179.

Naming documents puts every bidder on one basis. "Complies with international standards" leaves each supplier working to the system it knows well, and the quotes stop being comparable.

### Third-party inspection

Where a third party must witness the work, name the body, the scope, and who pays. Common bodies include SGS, BV, and TÜV, and the usual scope covers material traceability, weld inspection, and load test witnessing.

Two payment routes exist: fold the fee into the quote, or let the buyer pay the body directly. Either route works, yet the inquiry has to fix it, otherwise each bidder assumes something different.

### Factory acceptance and witnessing

State whether factory acceptance testing applies, and whether witnessing happens on site or by live video. Remote witnessing needs agreed camera positions, agreed lighting, and a list of items that remote work cannot cover, such as load preparation for the overload test.

Agree the test criteria as well. Static tests commonly run at 125% of rated load and dynamic tests at 110%, subject to the applicable standard and the contract.

| Inspection item | Common arrangement | What the inquiry must state |
| --------------- | ------------------ | --------------------------- |
| Material traceability | Certificates for main structural parts | Whether EN 10204 3.1 applies |
| Weld inspection | Visual check plus sampled NDT | Sampling ratio and acceptance level |
| No-load operation | Every mechanism over full travel | Whether a continuous running duration applies |
| Rated load test | Full rated load | Who prepares the test load |
| Static overload | Commonly 125% | Hold time and deformation measurement method |
| Dynamic overload | Commonly 110% | Braking distance record requirement |
| Remote witnessing | Live video plus screen recording | Which items remote work cannot cover |

## Commercial Terms to Fix Before the Quote

### Lead time and payment

Give the lead time a starting point. The usual wording reads "XX days from receipt of down payment and drawing approval". A bare "XX days" gets reinterpreted repeatedly during execution.

Payment milestones need the same treatment: down payment share, pre-shipment share, post-acceptance share, retention share, and the conditions for release. Those percentages reveal the real cash exposure better than the unit price does.

### Warranty and spares

Give the warranty a starting point too, whether shipment date, arrival date, or acceptance date. The three readings differ a great deal once a dispute starts.

List which spares ship with the machine and which stay optional. Put wear items such as brake linings, limit switches, and seals on the with-machine list, because buying them separately often takes longer than the machine itself.

## What a Good Reply Looks Like

### The structure a quotation should carry

A quote worth pursuing shows five traits: data-item answers, itemised pricing, listed exclusions, a drawing set, and references.

Itemised pricing matters more than the other four traits combined. It shows where the money goes: structure, mechanisms, electrical control, transport, and installation. A single total leaves you nothing to negotiate with, because there is no line to attack.

Yuzhong replies in that shape, with a data sheet, an itemised price, and exclusions on a separate page. The format is not there to look good. It lets a buyer compare three quotes line by line instead of comparing totals.

One note on timing. A reliable supplier returns a technical proposal and a first price within days of a complete inquiry. When a complete inquiry arrives with drawings, Yuzhong sends back a parameter confirmation sheet first. The buyer ticks each line, so definitions settle before price enters the conversation.

### Red flags

Watch for replies that dodge technical questions, fill key rows with "standard configuration", or refuse itemised pricing.

One pattern hides better. A quote comes in clearly below the others while the exclusions read "excludes rail, excludes installation, excludes commissioning, excludes training, excludes freight". Add up all those exclusions and the gap often doubles.

| Inquiry completeness | Spread across three quotes (experience) | Clarification rounds needed |
| -------------------- | --------------------------------------- | --------------------------- |
| Tonnage and span only | Can exceed 50% | Three or more, still not comparable |
| Ten data items added | Commonly 20%–35% | Around two |
| Ten items plus drawings and site photos | Commonly 10%–20% | One round settles the award |
| Standards, inspection, and commercial terms added | Commonly within 10% | Straight into the technical agreement |

## Frequently Asked Questions

### 1. What is the minimum data set for a usable quote?

Four items carry a usable quote: rated capacity with a note on attachment weight, span with its definition stated, lift height with its datum stated, and duty class or daily cycles. Those four still produce a quote, yet it will rest on assumptions. Add power supply, working environment, and control method and the error band narrows to something you can work with.

### 2. Can a supplier quote without building drawings?

Yes, though the result serves as a budget figure and not as a contract basis. The substitute is a hand-drawn cross-section with the key dimensions, namely column pitch, rail top elevation, and beam underside elevation, plus site photos. Suppliers accept sketches as a rule, and they rarely object. Missing dimensions are the real obstacle, not drawing quality.

### 3. How many suppliers should receive the inquiry?

Three works well. Two leave no cross-check, so one wrong definition leaves you with nothing to compare. Four or more cut the marginal gain fast while multiplying the clarification workload. The condition is identical inquiry documents to all three, because otherwise the count adds nothing.

### 4. How to force bidders onto one basis?

Attach a fixed-format parameter and price comparison sheet, and require line-by-line completion with a header note saying "blank means excluded". Add a second rule: any departure from the inquiry must appear on its own list with a reason attached. Those two rules surface most definition gaps before the quotes arrive.

### 5. How long does crane delivery usually take?

For standard [single-girder](https://yzcranes.com/product-category/single-girder-overhead-crane/) or double-girder electric overhead cranes, 45–90 days covers most cases. Heavy capacity, special environments such as explosion-proof, cleanroom, or low temperature, and highly customised projects all run longer. Fix the starting point, whether down payment, drawing approval, or letter of credit, because "60 days" spans a month of difference across those three.